Project Update - Park Lane Mews
6th November 2025
Works on the upper levels are largely complete, allowing focus to shift toward the ground floor glazing, aluminium rainscreen installation, and the commencement of the first fix for the GRC cladding.
These activities will continue into the early part of 2026.